Transition Process Schedule & Estimated Milestones Dates
Version 1.9
(Living document)
Five (5) YearTime Line
CY 2008
Complete prospective for potential sale of Peace East
Design External storage and complete cost estimates
Obtain cost estimates for Temporary Sunday School Classrooms
Establish Latch Key Program
Meet and share with our neighbors 
Develop moving step plans (A & B) for PE to PW
Build relationship with Roger’s Planning and Zoning staff and board 
MILESTONE – (July) Present progress and request funds for
professional fees to complete space requirements & Worship Center
floor plan concepts
Conduct interviews, select firm for a Capital Investment Program
Conduct interviews and select Architectural Firm for Worship Center
area
Complete PW Worship Center minimum space requirements
Complete draft of floor plan for Worship Center
Meet, share and gather input and concerns from with our
neighborhood communities on PW future plans
MILESTONE – (November) Present space requirements & Worship
Center concepts & secure approval for fees to begin design of
Worship Center & Storage phase
Implement the Capital Investment Program