![]() Hire the selected Architectural firm for Peace West Worship Center
Hold a pre-bid contractor qualification reviews and interviews and
select 3-5 firms.
Establish Entities to manage and operate SmB and SH
CY 2009
Complete schematic design and working model of WC
MILESTONE (February) Present floor plans and draft concept of
Worship Center, Storage and Parking lot and gather input on exterior
concepts
Meet and share with our neighbors
Complete Final for floor plan and exterior plans Worship Center
design
Complete Cost Estimate for PW Worship Center & Parking Lot
MILESTONE (May) Present Worship Center Plans schematic design,
temporary portable rooms, external storage plans and estimated
construction Costs and secure approval for what is to be done
Meet and share with our neighbors
Secure Planning permits and approval
Complete construction documents and final plans for Worship Center
and External Storage phase
Secure Rogers Planning Permits and Approval for External Storage
Hold bid letting, make contract approval on External Storage
Move the Metal shed and complete redesign of storage
Complete Senior Housing Exploratory Recommendations
MILESTONE (July) - Present Senior Housing finding and concepts,
and draft layouts for columbarium, memorial gardens and recreation
fields
|